Scope of Work:

  • Demolish and remove approximately (48,450 sf) of asphalt at 4” 
  • Hauling away removed asphalt, Remove tree roots in 4 areas that are raising asphalt, Fine grade & Re-compact at approximately 38,000 sf.
  • Import subbase materials as needed to make sub structural base to receive asphalt.
  • Take off edges and prepare for new hot asphalt, 
  • Repave / Import 38,000 sf parking lot at 4” with 1/2” Reg. PG 64-10 Asphalt Includes re-establish asphalt Swale on west side of parking lot to direct water runoff to drain
  • Install 6” AC Berm in kind at south driveway entrance (24 lf)
  • Power clean existing asphalt of loose dirt and debris.
  • Apply (1) coat of sealer to approximately (48,450 sf) of asphalt
  • Reinstall those that can be reused and replace all damaged wheel stops with new one (74 EA)
  • Re-stripe pavement marking to original layout.